• Del Valle High School


    SCOPE OF WORK

     
    Completed Scope:
    • Secure Front Entry (Completed August 2016)
    • New Multi-Purpose Turf at Stadium (Completed August 2016)
    • Gymnasium Bleacher and Floor Replacements (Completed November 2016)
    • New Baseball, Softball, and Tennis lighting (Completed January 2017)
    • New Baseball / Softball Fields' Sound System, Outfield Fencing, and Scoreboard (Completed January 2017)
     
    Combined with Bond 2019:
    • Fire Safety System Upgrades
    • Security System Upgrades
    • PA / Notification Systems Upgrades
    • Wireless, Bandwidth, and Infrastructure Technology Upgrades
    • New backboards that retract for cross-court tournament and practice play
    • Roof Replacement
    • Electrical Upgrades and Replacement
    • HVAC Replacement
    • Building Envelope Renovations
    • Restroom Upgrades
  • Budget: $6,525,853*

    *This total is based on an anticipated project schedule and adjusted for inflation.  Project totals may change based on revised project schedules during the course of the five year bond.

  • ESTIMATED PROJECT COST**

    AMOUNT PER CATEGORY

    Budgeted Scope:

    • Safety & Security - $111,411
    • Technology - $540,090
    • Athletics - $4,231,425
    • Replacements & Renovations - $1,642,927

     

    **Project Cost includes the cost of construction, design fees, permitting, testing, hazardous, materials testing, fixtures, furniture, and equipment (for addition and new building only), technology, (for addition and new building only) and inflation based on schedule.

     

     

     

  • Please submit your question(s) or suggestion(s) about this school project to bond@yisd.net and a YISD representative will follow up.