Eastwood High School Construction

  • Eastwood High School


    SCOPE OF WORK

    Completed Scope:
    • New Multi-Purpose Turf at Stadium (Completed August 2016)
    • Tennis lighting (Completed January 2017)
    • New Softball (Scotsdale Elementary Site) lighting (Completed February 2017)
    • New Softball Field (Scotsdale Elementary Site) Sound System, Outfield Fencing, and Scoreboard (Completed February 2017)
    • Portable Village (Completed August 2017)
     
    Under Construction: (Estimated Completion Fall 2019)
    • Secure Front Entry
    • Wireless, Bandwidth, and Infrastructure Technology Upgrades
    • New fully comprehensive, 21st Century high school to accommodated 2,200 students
    • Safe and secure campus with robust technology, STEM, and renovated Fine Arts spaces
    • Replacement of the oldest parts of the campus (51 years old)
    • Maintenance of the newest and most viable parts of the campus
    • New Baseball lighting
    • Gymnasium bleacher and backboard replacements
    • New Baseball fields' sound system, outfield fencing, and scoreboard
  • ESTIMATED PROJECT COST**

    AMOUNT PER CATEGORY

    Budgeted Scope:

    • Safety & Security - $25,300
    • Technology - $540,090
    • Additions & Renovations - $93,039,250
    • Athletics - $2,713,425

     

    **Project Cost includes the cost of construction, design fees, permitting, testing, hazardous, materials testing, fixtures, furniture, and equipment (for addition and new building only), technology, (for addition and new building only) and inflation based on schedule.

     

     

     

  • Please submit your question(s) or suggestion(s) about this school project to bond@yisd.net and a YISD representative will follow up.