• J.M. Hanks High School


    SCOPE OF WORK

     
    Completed Scope:
    • Secure Front Entry (Completed August 2016)
    • New Multi-Purpose Turf (Completed August 2016)
    • New Baseball and Softball lighting (Completed January 2017)
    • New Baseball / Softball fields' sound system, outfield fencing, and scoreboard (Completed January 2017)
    • New Tennis Court Lighting (Completed March 2017)
    • New Safe, Secure and Accessible Retractable Bleachers (Completed November 2017)
     
    Under Construction: (Estimated Completion Fall 2018)
    • Security System Upgrades
    • PA / Notification Systems Upgrades
    • Wireless, Bandwidth, and Infrastructure Technology Upgrades
    • New backboards that retract for cross-court tournament and practice play
    • Roof Replacement
    • Electrical Upgrades and Replacement
    • HVAC Replacement
    • Restroom Upgrades
  • Budget: $13,361,360*

    *This total is based on an anticipated project schedule and adjusted for inflation.  Project totals may change based on revised project schedules during the course of the five year bond.

  • ESTIMATED PROJECT COST**

    AMOUNT PER CATEGORY

    Budgeted Scope:

    • Safety & Security - $794,861
    • Technology - $540,090
    • Athletics - $3,092,925
    • Replacements & Renovations - $8,933,484

     

    **Project Cost includes the cost of construction, design fees, permitting, testing, hazardous, materials testing, fixtures, furniture, and equipment (for addition and new building only), technology, (for addition and new building only) and inflation based on schedule.

     

     

     