    Completed Scope:
    • Secure Front Entry (Completed August 2016)
    • New Multi-Purpose Turf (Completed August 2016)
    • New Baseball, Softball, and Tennis lighting (Completed January 2017)
    • New Baseball / Softball fields' sound system, outfield fencing, and scoreboard (Completed January 2017)
    • Fire Safety System Upgrades (Completed Summer 2019)
    • Security System Upgrades (Completed Summer 2019)  
    • PA / Notification Systems Upgrades (Completed Summer 2019)  
    • Roof Replacement (Completed Summer 2019)  
    • Wireless, Bandwith, and Infrastructure Technology Upgrades (Completed Summer 2019)  
    • JROTC Facility Upgrades(Completed Summer 2019)  
    • Classroom Renovations for T-STEM Early College High School at Parkland High School (Completed Summer 2019)  
    • New blackboards that retract for cross-court tournament and practice play (Completed Summer 2019)  
    • New safe, secure, and accessible bleachers (Completed Summer 2019)  

     

  • Budget: $11,179,287*

    *This total is based on an anticipated project schedule and adjusted for inflation.  Project totals may change based on revised project schedules during the course of the five year bond.

  • ESTIMATED PROJECT COST**

    AMOUNT PER CATEGORY

    Budgeted Scope:

    • Safety & Security - $920,318
    • Technology - $540,090
    • Additions & Renovations - $2,530,000
    • Athletics - $3,092,925
    • Replacements & Renovations - $4,095,954

     

    **Project Cost includes the cost of construction, design fees, permitting, testing, hazardous, materials testing, fixtures, furniture, and equipment (for addition and new building only), technology, (for addition and new building only) and inflation based on schedule.

     

     

     