• Parkland High School


    SCOPE OF WORK

     
    Completed Scope:
    • Secure Front Entry (Completed August 2016)
    • New Multi-Purpose Turf (Completed August 2016)
    • New Baseball, Softball, and Tennis lighting (Completed January 2017)
    • New Baseball / Softball fields' sound system, outfield fencing, and scoreboard (Completed January 2017)
     
    Under Construction: (Estimated Completion Summer 2019)
    • Fire Safety System Upgrades
    • Security System Upgrades
    • PA / Notification Systems Upgrades
    • Roof Replacement
    • Wireless, Bandwidth, and Infrastructure Technology Upgrades
    • JROTC Facility Upgrades
    • Classroom Renovations for T-STEM Early College High School at Parkland High School
    • New backboards that retract for cross-court tournament and practice play
    • New safe, secure, and accessible bleachers
  • Budget: $11,179,287*

    *This total is based on an anticipated project schedule and adjusted for inflation.  Project totals may change based on revised project schedules during the course of the five year bond.

  • ESTIMATED PROJECT COST**

    AMOUNT PER CATEGORY

    Budgeted Scope:

    • Safety & Security - $920,318
    • Technology - $540,090
    • Additions & Renovations - $2,530,000
    • Athletics - $3,092,925
    • Replacements & Renovations - $4,095,954

     

    **Project Cost includes the cost of construction, design fees, permitting, testing, hazardous, materials testing, fixtures, furniture, and equipment (for addition and new building only), technology, (for addition and new building only) and inflation based on schedule.

     

     

     

  • Please submit your question(s) or suggestion(s) about this school project to bond@yisd.net and a YISD representative will follow up.