• Rio Bravo Middle School


    SCOPE OF WORK

    Completed Scope:
    • Secure Front Entry (Completed August 2016)
    • Roof Replacement (Completed Summer 2017)
    • HVAC Replacement (Completed Summer 2017)
    • Building Envelope Renovations (Completed Summer 2017)
    • Restroom Upgrades (Completed Summer 2017)
    • New gymnasium for middle school athletics and competitions (Completed Fall 2017)
    • New boys and girls locker rooms (Completed Fall 2017)
    • Wireless, Bandwith, and Infrastructure Technology Upgrades (Completed)
     
  • Budget: $8,453,878*

    *This total is based on an anticipated project schedule and adjusted for inflation.  Project totals may change based on revised project schedules during the course of the five year bond.

  • ESTIMATED PROJECT COST**

    AMOUNT PER CATEGORY

    Budgeted Scope:

    • Safety & Security - $25,300
    • Athletics - $7,851,500
    • Replacements & Renovations - $339,298
    • Technology - $237,780

     

    **Project Cost includes the cost of construction, design fees, permitting, testing, hazardous, materials testing, fixtures, furniture, and equipment (for addition and new building only), technology, (for addition and new building only) and inflation based on schedule.

     

     

     

  • Please submit your question(s) or suggestion(s) about this school project to bond@yisd.net and a YISD representative will follow up.