• Tierra Del Sol Elementary School


    SCOPE OF WORK

     
    Completed Scope:
    • Secure Front Entry (Completed August 2016)
    • New kitchen and cafeteria space to adequately serve student population (Completed October 2017)
    • Provides separate activity room from existing cafeteria for proper physical education programs and scheduling (Completed October 2017)
    • Building Envelope Renovations (Completed October 2017)
    • Restroom Upgrades (Completed October 2017)
    • Security System Upgrades (Completed October 2017)
    • PA / Notification Systems Upgrades (Completed October 2017)
    • Roof Replacement (Completed Fall 2017)
    • Electrical Upgrades and Replacement (Completed Fall 2017)
    • HVAC Replacement (Completed Fall 2017)
    • Wireless, Bandwith, and Infrastructure Technology Upgrades (Completed)

     

  • Budget: $5,173,686*

    *This total is based on an anticipated project schedule and adjusted for inflation.  Project totals may change based on revised project schedules during the course of the five year bond.

  • ESTIMATED PROJECT COST**

    AMOUNT PER CATEGORY

    Budgeted Scope:

    • Safety & Security - $552,116
    • Additions & Renovations - $3,454,250
    • Replacements & Renovations - $1,049,237
    • Technology - $118,083

     

    **Project Cost includes the cost of construction, design fees, permitting, testing, hazardous, materials testing, fixtures, furniture, and equipment (for addition and new building only), technology, (for addition and new building only) and inflation based on schedule.

     

     

     

  • Please submit your question(s) or suggestion(s) about this school project to bond@yisd.net and a YISD representative will follow up.