Campus
- Home
- Alicia R. Chacon Int'l School
- Ascarate Elementary School
- Bel Air High School
- Bel Air Middle School
- Capistrano Elementary School
- Cedar Grove Elementary School
- Cesar Chavez Academy
- Constance Hulbert Elementary School
- Del Norte Heights Elementary School
- Del Valle Elementary School
- Del Valle High School
- Desert View Middle School
- Desertaire Elementary School
- Dolphin Terrace Elementary School
- East Point Elementary School
- Eastwood Heights Elementary School
- Eastwood High School
- Eastwood Knolls International School
- Eastwood Middle School
- Edgemere Elementary School
- Glen Cove Elementary School
- Hacienda Heights Elementary School
- Indian Ridge Middle School
- J.M. Hanks High School
- Lancaster Elementary School
- LeBarron Park Elementary School
- Loma Terrace Elementary School
- Marian Manor Elementary School
- Mesa Vista Elementary School
- New Del Valle Middle | Mission Valley Elementary Combo School
- North Loop Elementary School
- North Star Elementary School
- Parkland Elementary School
- Parkland High School
- Parkland Middle School
- Parkland Pre-K Center
- Pasodale Elementary School
- Pebble Hills Elementary School
- Presa Elementary School
- R.E.L. Washington Elementary School
- Ramona Elementary School
- Rio Bravo Middle School
- Riverside High School
- Riverside Middle School
- Sageland Elementary School
- Scotsdale Elementary School
- Thomas Manor Elementary School
- Tierra Del Sol Elementary School
- Vista Hills Elementary School
- Ysleta Elementary School
- Ysleta High School
- Ysleta Middle School
- Ysleta Pre-K Center
- YISD Bond 2015
- Parkland Middle School






-
Parkland Middle School
SCOPE OF WORK
Completed Scope:- Phase I Construction
- Utilities (Completed August 2016)
- Phase II Construction
- Demolition (Completed October 2016)
- Fire Safety System Upgrades (Completed Summer 2017)
- Restroom Upgrades (Completed Summer 2017)
- HVAC Replacements (Completed Summer 2017)
- Electrical Upgrades and Replacement (Completed Summer 2017)
- Plumbing System Replacement (Completed Summer 2017)
- Roof Replacement (Completed Summer 2017)
- Phase III Construction: (Completed Fall 2017)
- Secure Front Entry (Completed Fall 2017)
- PA / Notification Systems Upgrades (Completed Fall 2017)
- Administration and classroom area to be modernized and enlarged (Administration completed Fall 2017 and classroom completed August 2015)
Pending Scope:- Wireless, Bandwidth, and Infrastructure Technology Upgrades
-
Budget: $17,081,385*
*This total is based on an anticipated project schedule and adjusted for inflation. Project totals may change based on revised project schedules during the course of the five year bond.
-
ESTIMATED PROJECT COST**
AMOUNT PER CATEGORY
Budgeted Scope:
- Safety & Security - $489,971
- Technology - $237,780
- Additions & Renovations - $14,360,250
- Replacements & Renovations - $1,993,384
**Project Cost includes the cost of construction, design fees, permitting, testing, hazardous, materials testing, fixtures, furniture, and equipment (for addition and new building only), technology, (for addition and new building only) and inflation based on schedule.
CONSTRUCTION PROGRESS
-
Please submit your question(s) or suggestion(s) about this school project to bond@yisd.net and a YISD representative will follow up.