• LeBarron Park Elementary School / NEW Alicia Chacon Elementary School


    SCOPE OF WORK

     
    Completed Scope:
    • Secure Front Entry (Completed August 2016)
    • Wireless, Bandwidth, and Infrastructure Technology Upgrades (Completed Summer 2018)
    • New kitchen and cafeteria space to adequately serve student population (Completed Summer 2018)
    • Provides separate activity room from existing cafeteria for proper physical education programs and scheduling (Completed Summer 2018)
    • Plumbing System Replacement (Completed Summer 2018)
    • Roof Replacement (Completed Summer 2018)
    • Electrical Upgrades and Replacement (Completed Summer 2018)
    • HVAC Replacement (Completed Summer 2018)
    • Restroom Upgrades (Completed Summer 2018)
     
  • Budget: $5,500,328*

    *This total is based on an anticipated project schedule and adjusted for inflation.  Project totals may change based on revised project schedules during the course of the five year bond.

  • ESTIMATED PROJECT COST**

    AMOUNT PER CATEGORY

    Budgeted Scope:

    • Safety & Security - $25,300
    • Technology - $118,083
    • Additions & Renovations - $3,485,000
    • Replacements & Renovations - $1,871,945

     

    **Project Cost includes the cost of construction, design fees, permitting, testing, hazardous, materials testing, fixtures, furniture, and equipment (for addition and new building only), technology, (for addition and new building only) and inflation based on schedule.

     

     

     

  • Please submit your question(s) or suggestion(s) about this school project to bond@yisd.net and a YISD representative will follow up.